Quiz · Medium
Twenty questions on takt time, EOQ, OEE, learning curves, reliability, capability and queueing.
A cell must produce 480 units in a 480-minute shift with 30 minutes of breaks. What is the takt time?
1.0 min
0.89 min
1.06 min
0.94 min
Available time = 480 - 30 = 450 min; 450/480 = 0.94 min. Using 480 ignores the breaks (1.0).
Which is NOT one of the classic seven lean wastes?
Overproduction
Automation
Waiting
Defects
Automation is a tool, not a waste. The others are on the list (overproduction, waiting, defects, plus transport, inventory, motion, over-processing).
Average WIP is 40 jobs and the plant ships 8 jobs per day. By Little's law the average time in the system is:
320 days
0.2 days
5 days
48 days
W = L / lambda = 40/8 = 5 days. 0.2 comes from inverting the ratio.
D = 2,000 units/yr, S = $40/order, H = $4/unit-yr. EOQ is:
632
80
200
400
Q = sqrt(2*2000*40/4) = sqrt(40000) = 200. 632 comes from forgetting to divide by H.
At the EOQ:
Ordering cost is zero
Holding cost is double ordering cost
Ordering cost equals holding cost
Total cost is zero
Total cost is minimized where annual ordering cost equals annual holding cost.
Which scheduling rule minimizes mean flow time on one machine?
FCFS
SPT
Longest processing time
EDD
SPT. EDD minimizes maximum lateness; FCFS has no optimality property.
A machine: availability 85%, performance 90%, quality 96%. OEE is closest to:
73%
77%
85%
90%
0.85 x 0.90 x 0.96 = 0.734. Averaging the three (90%) is the common mistake.
An 80% learning curve: unit 1 takes 50 hours. Unit 4 takes:
30 h
32 h
40 h
20 h
Two doublings: 50 x 0.8 x 0.8 = 32 hours.
Three components in series have reliabilities 0.95, 0.90 and 0.98. System reliability is:
0.90
0.838
0.95
0.977
Series: 0.95 x 0.90 x 0.98 = 0.838. It must be below the weakest component (0.90).
A process has Cp = 1.8 but Cpk = 0.7. The best conclusion is:
The process is off-center
The process variation is too large
The process is capable and centered
The specification is too tight
Cp ignores centering and is good here, so the large gap to Cpk means the mean is far from the target.
A control chart point falls above the UCL. This most likely indicates:
That the process is capable
A bad sample size
A special cause
Normal random variation
Points outside 3 sigma limits are rare under common cause variation (about 0.27%), so look for an assignable cause.
Which tool ranks defect types by frequency to find the vital few?
Pareto chart
Scatter plot
Fishbone diagram
Gantt chart
The Pareto chart. A fishbone organizes possible causes but does not rank frequencies.
An M/M/1 queue has arrivals 6/h and service rate 8/h. Average time in the system is:
15 min
30 min
45 min
22.5 min
W = 1/(mu - lambda) = 1/2 h = 30 min. 22.5 min is the time in the queue only (Wq = lambda/(mu(mu-lambda))).
Assembly tasks total 150 s and cycle time is 50 s. The minimum number of stations is:
2
4
3
5
150/50 = 3 stations.
In time study, normal time is:
Observed time x rating factor
Standard time / rating
Observed time x (1 + allowance)
Cycle time / takt
Normal time = observed x rating. Allowances are then added to get standard time.
Which layout fits low-volume, high-variety production?
Assembly line
Fixed-position layout
Process layout
Product layout
Process (functional) layout groups similar machines and supports variety. Product layouts suit high volume, standard products.
The bullwhip effect describes:
Production halting on a defect
Demand variance amplifying upstream in a supply chain
Forecast error shrinking with aggregation
Queues forming at a bottleneck
Orders become more variable than sales as you move upstream.
Fixed cost $30,000; price $80; variable cost $50. Break-even volume:
1,000 units
1,600 units
375 units
600 units
30000 / (80 - 50) = 1000 units. 375 comes from dividing by the price alone.
According to the Theory of Constraints, after identifying the constraint you should:
Elevate it first
Add capacity to non-constraints
Remove all buffers
Exploit it
Step 2 is to exploit the constraint (get the most from it); elevating comes later.
True or false: Cpk can be larger than Cp.
True
False
Cpk = Cp x (1 - k) where k measures off-centering, so Cpk <= Cp, with equality only when centered.