Quiz · Hard
Multi-step operations problems: EOQ cost, newsvendor, safety stock, PERT and critical path, learning curve, takt time, Cpk, forecasting and earned value.
Forecast errors (actual minus forecast) over four periods were +10, -20, +15 and -5. What is the MAD?
0
10
12.5
15
MAD = (10 + 20 + 15 + 5)/4 = 12.5. The net error is 0, which hides large offsetting errors, and why absolute values are used.
Annual demand is 10,000 units, ordering cost is $40 and holding cost is $2 per unit per year. At the EOQ, about how much is the annual holding cost?
$316
$632
$1,265
$2,000
EOQ = sqrt(2 x 10,000 x 40 / 2) = 632.5. Holding cost = (Q/2) x H = 316.2 x 2 = $632. At the EOQ, ordering cost ($632) equals holding cost, so the total is about $1,265.
A newsvendor buys at $6, sells at $10 and gets $5 salvage for unsold units. What is the optimal critical ratio?
0.40
0.50
0.80
0.20
Cu = 10 - 6 = 4 and Co = 6 - 5 = 1. CR = 4/(4+1) = 0.80. Order up to the demand level with 80% cumulative probability.
Daily demand has a standard deviation of 20 units, lead time is 9 days and the target service level corresponds to z = 1.65. What is the safety stock?
About 99 units
About 33 units
About 297 units
About 330 units
SS = z x sigma_d x sqrt(L) = 1.65 x 20 x 3 = 99. Multiplying by L instead of its square root gives 297.
An activity has optimistic, most likely and pessimistic times of 6, 10 and 20 days. What is the PERT expected time?
10 days
11 days
12 days
13 days
te = (6 + 4x10 + 20)/6 = 66/6 = 11. The simple average of the three numbers would be 12.
A project network has activities A (3 days) then B (4) and C (6) in parallel, then D (2), then E (3). B and C both follow A and both precede D. What is the project duration?
12 days
13 days
14 days
18 days
Paths: A-B-D-E = 12 and A-C-D-E = 14. The longest path (critical) is 14 days. 18 would be the sum of B and C as if they were in series, which ignores that they run in parallel.
In the same network, how much float does activity B have?
0 days
2 days
4 days
6 days
B is on the 12-day path, 2 days shorter than the 14-day critical path, so it can slip 2 days without delaying the project. C is critical with zero float.
The first unit of a product takes 100 hours and production follows an 80% learning curve. How long will the 4th unit take?
64 hours
80 hours
60 hours
40 hours
Doubling output from 1 to 2 units gives 80 hours for unit 2. Doubling again from 2 to 4 gives 0.8 x 80 = 64 hours for unit 4. Cumulative average is not what is asked.
Fixed costs are $90,000, price per unit is $25 and variable cost is $10. How much profit at 8,000 units?
$15,000
$30,000
$80,000
$110,000
Contribution = $15 per unit. Break-even is 6,000 units. At 8,000 units profit = 8,000 x 15 - 90,000 = $30,000. $110,000 forgets fixed costs.
There are 450 minutes of production time per shift and demand of 150 units. A station needs 3.5 minutes per unit. What is the issue?
Takt time is 3.5 minutes, so it is balanced
Takt time of 0.33 minutes means no action needed
Cycle time and takt time are unrelated
Cycle time of 3.5 exceeds takt time of 3.0, so demand cannot be met by this station
Takt = 450/150 = 3 minutes. A station slower than takt is a constraint. It could meet only 450/3.5 = 128 units.
A process has mean 50, standard deviation 2, LSL 42 and USL 60. What is Cpk?
1.67
1.00
1.33
2.50
Upper: (60 - 50)/(3 x 2) = 1.67. Lower: (50 - 42)/6 = 1.33. Cpk takes the smaller value, 1.33. Cp (ignoring centering) = 18/12 = 1.5.
On a control chart, eight consecutive points fall above the center line but within the control limits. What does this suggest?
A likely shift in the process mean (special cause)
The process is in control, so no action is needed
The control limits are too narrow
The data were measured incorrectly
Run rules flag non-random patterns even inside limits. A sequence of points on one side of the center line is very unlikely by chance. It is not proof of measurement error.
A firm last forecast 200 units, actual demand was 220 and alpha is 0.3. What is the next exponential smoothing forecast?
210
206
214
220
F = 0.3(220) + 0.7(200) = 66 + 140 = 206. Alpha near 1 would track the latest actual more closely.
A cell has 240 units of WIP and an average flow time of 8 hours. What is the throughput?
32 units per hour
30 units per hour
1,920 units per hour
0.033 units per hour
Throughput = WIP / flow time = 240/8 = 30. Multiplying WIP by flow time gives a meaningless 1,920.
COGS is $6.0 million and average inventory is $1.0 million. Approximately how many days of inventory does the firm hold?
61 days
6 days
30 days
365 days
Turnover = 6.0/1.0 = 6 times a year. Days of inventory = 365/6 = 60.8, about 61 days.
A project has EV of $60,000, AC of $75,000 and PV of $50,000. Which statement is correct?
Under budget and ahead of schedule
Over budget and behind schedule
Over budget and ahead of schedule
Under budget and behind schedule
CPI = 60/75 = 0.80 (over budget). SPI = 60/50 = 1.20 (ahead of schedule). Less than 1 is bad for cost, greater than 1 is good for schedule.
A kanban loop has demand of 60 units per hour, a replenishment lead time of 2 hours, a 10% safety factor and containers of 11 units. How many kanbans are needed?
12
11
10
13
Kanbans = demand x lead time x (1 + safety) / container size = 60 x 2 x 1.1 / 11 = 12.