Quiz · Medium
Process types, capacity, Little's law, quality tools, Six Sigma, lean wastes, EOQ and supply chain basics with diagrams and short calculations.
A workshop builds one-off custom kitchens, each different from the last, using general-purpose machines and skilled workers. Which process type is this?
Mass production
Continuous process
Jobbing (job shop)
Batch with standard products
Very low volume and high variety fit a job shop. Mass and continuous processes need high volume and standardized output.
The image illustrates the bullwhip effect. Which of the following is a recognized CAUSE?

Sharing point-of-sale data
Order batching
Vendor-managed inventory
Smaller, more frequent orders
Batching orders (weekly or monthly) distorts demand signals upstream. The others are remedies. Image: Thwongterry, Toobaz, Stern, CC BY-SA 3.0, via Wikimedia Commons.
The photograph shows a 1923 car assembly line. Which statement best describes this type of process?

High volume, low variety, with a fixed sequence of tasks
Low volume, high variety, with general-purpose machines
One-off project with a unique output
Continuous flow of a homogeneous product
Assembly lines are mass (line) processes. A job shop is low volume and high variety, a project is unique, and continuous processes (refining, chemicals) handle homogeneous output. Image: Peter Elfelt, public domain, via Wikimedia Commons.
In Hill's framework, an order winner is:
A minimum standard needed to be considered at all
The criterion that makes customers choose a product over its rivals
The product with the highest sales volume
A supplier who wins an order by competitive bidding
Qualifiers get you into consideration, winners get you the order. The two change over time as competitors catch up.
A line has a design capacity of 500 units per day and an effective capacity of 400. Actual output is 360. What is the efficiency?
72%
80%
110%
90%
Efficiency = actual / effective = 360/400 = 90%. Utilization = 360/500 = 72% (uses design capacity). 80% is effective/design.
A hospital groups all radiology equipment in one department and routes patients to it as needed. Which layout is this?
Product layout
Process (functional) layout
Fixed-position layout
Cellular layout
Similar resources are grouped by function and the patient moves between them, which suits high variety. Product layouts follow a fixed sequence.
A service system handles 30 customers per hour and, on average, 120 customers are in the system. By Little's Law, the average time a customer spends in the system is:
0.25 hours
90 hours
4 hours
150 hours
WIP = throughput x flow time, so flow time = 120/30 = 4 hours. 0.25 is the inverse (30/120).
Stations in a three-step process take 4, 6 and 5 minutes per unit. What is the maximum output per hour?
10 units
12 units
15 units
20 units
The 6-minute station is the bottleneck: 60/6 = 10 units per hour. Output cannot exceed the slowest step.
A plant has 480 available minutes per shift and customer demand of 96 units per shift. What is the takt time?
0.2 minutes per unit
5 minutes per unit
4.8 minutes per unit
96 minutes per unit
Takt time = available time / demand = 480/96 = 5 minutes.
In the Deming cycle shown, which stage follows 'Do'?

Plan
Act
Check
Standardize
The order is Plan, Do, Check, Act. Check (study) evaluates results before acting. Image: DSP-user, public domain, via Wikimedia Commons.
A company spends heavily on employee training and preventive maintenance to avoid defects. In the cost of quality framework, these are:
Prevention costs
Appraisal costs
Internal failure costs
External failure costs
Prevention costs are incurred to stop defects occurring. Appraisal means inspection and testing, and failure costs arise once defects exist.
In the cause-and-effect diagram shown, what does the box at the head of the fish represent?

The most likely root cause
The problem (effect) being investigated
The corrective action
The process owner
Causes are grouped on the bones leading to the effect at the head. Image: FabianLange at de.wikipedia, CC BY-SA 3.0, via Wikimedia Commons.
On the control chart shown, one sample falls above the UCL line. What should the manager do?

Ignore it because it is only common-cause variation
Widen the control limits
Change the specification limits
Investigate for a special (assignable) cause
A point beyond the control limits signals an unusual cause. Widening limits to hide it defeats the purpose of SPC. Image: DanielPenfield, public domain, via Wikimedia Commons.
Using the Pareto chart shown, roughly what share of late arrivals do the two largest causes (traffic and child care) explain?

About 60%
About 25%
About 35%
About 90%
Traffic (55) plus child care (40) is 95 out of 155 late arrivals, about 61%. Image: Dense2013, CC BY-SA 4.0, via Wikimedia Commons.
A Six Sigma process is expected to produce approximately how many defects per million opportunities?
34
233
3.4
6,210
6 sigma corresponds to 3.4 DPMO. 233 is 5 sigma and 6,210 is 4 sigma (with the 1.5 sigma shift).
What is the correct order of the first three steps in DMAIC?
Measure, Define, Improve
Define, Measure, Analyze
Define, Analyze, Measure
Analyze, Define, Control
DMAIC: Define, Measure, Analyze, Improve, Control. You define the problem, measure the baseline, then analyze causes.
Which lean waste is described as 'producing ahead of demand'?

Over-production
Over-processing
Inventory
Transport
Over-production makes more than customers need now and causes excess inventory and other wastes. Over-processing means doing unnecessary work on a unit. Image: Dirk Pons, CC BY 4.0, via Wikimedia Commons.
In 5S, 'Seiton' means:
Sort out unneeded items
Shine and clean
Set in order (a place for everything)
Sustain the discipline
Seiri = sort, Seiton = set in order, Seiso = shine, Seiketsu = standardize, Shitsuke = sustain.
The kanban board shown limits the number of items in 'Doing'. What principle of lean does this support?

Push production based on forecasts
Increasing batch sizes
Maximizing machine utilization
Pull and limiting work in progress
WIP limits keep flow smooth and expose bottlenecks, in line with a pull system. Image: Jennifer Falco, CC BY 4.0, via Wikimedia Commons.
After identifying the system's constraint, the next step in the Theory of Constraints is to:
Exploit the constraint (get the most from it)
Elevate the constraint immediately
Subordinate everything else to it
Remove all buffers
The five focusing steps are identify, exploit, subordinate, elevate, repeat. Elevating (investing) comes after getting the most out of existing capacity.
Annual demand is 4,800 units, ordering cost is $25 per order and holding cost is $6 per unit per year. What is the EOQ?
100 units
200 units
400 units
800 units
EOQ = sqrt(2 x 4800 x 25 / 6) = sqrt(40,000) = 200.
Demand is 30 units per day, lead time is 4 days and safety stock is 20 units. What is the reorder point?
140 units
120 units
150 units
100 units
ROP = d x L + SS = 30 x 4 + 20 = 140.
In ABC inventory analysis, class A items are:
The majority of items with the lowest value
Items with the shortest lead time
A small share of items with a large share of annual usage value
Items that are never counted
A items typically represent perhaps 10-20% of items and 70-80% of value, so they warrant tight control.
In the Kraljic matrix, which purchasing approach suits items with high profit impact AND high supply risk?

Competitive bidding and aggressive negotiation
Simplify and automate ordering
Stockpile and accept whatever the market offers
Strategic partnership and securing long-term supply
High impact and high risk items are strategic. Competitive bidding suits leverage items and simplified ordering suits non-critical items.
In the Gantt chart shown, an arrow labeled 'finish-to-start' between Activities B and C means:

C cannot finish until B finishes
C cannot start until B finishes
C starts when B starts
B and C finish together
Finish-to-start is the most common dependency. Start-to-start and finish-to-finish are the other types shown.